New Hassocks underpass provides safe public route

 A new railway underpass has opened at Hassocks, providing a safer and more accessible route for pedestrians and cyclists.

The new structure, partly funded by developer contributions, replaces the Woodside level crossing which closed in summer 2021.

The majority of the work was completed over a nine-day closure of the Brighton Main Line in February 2022, when Network Rail carried out upgrades at 30 worksites as part of a £15m investment.

A feat of engineering, 22,000 tonnes of earth were removed from the railway embankment before pre-cast concrete sections were slid into place to form the underpass structure. The embankment was then reinstated, and the railway put back over it.

Cllr Kirsty Lord, West Sussex County Council, said: "In recent years, the proposed new housing and school in this part of Hassocks increased the concerns of local residents and councillors about the safety and accessibility of Woodside crossing. I am relieved that our concerns were heard and would like to thank Network Rail for delivering this tunnel and for their efforts to minimise disruption to local residents. I am delighted that both new and old Hassocks residents will now have a safer and more accessible route between their homes and village facilities, and that it will also provide a great new route for local walkers and cyclists."

Cllr Sue Hatton, Mid Sussex District Council, added: "We have been extremely concerned about safety on the old crossing for some time. This concern grew as the proximity of new housing to the railway line increased. I am personally very grateful that Taylor Wimpey and Rydon got together with Network Rail to enable this superb tunnel to be provided. A feat of engineering as they say, and in a timely way under difficult and restricting circumstances."

Cllr Ian Weir, Hassocks Parish Council, said: "The whole community will benefit from this amazing new tunnel. It will form a key part of the network of safe off-road routes that the Parish Council is supporting around Hassocks to enable young people to travel independently to school and the village centre and for other residents to have cycling as an option for shorter journeys. Everywhere I hear positive comments about the brilliant job Network Rail have done and the care taken to cause the minimum disruption to local residents during construction." 

The Partnership Working Model which will deliver l...
Urban Park proposed for Burgess Hill